Solar PV Permit Submission Checklist

San Diego, California

Verify before submissionLast verified: Feb 15, 20266 verified sources

Solar PV Permit Checklist

San Diego13 required, 2 optional

Forms & Applications(3)

  • Permit ApplicationREQUIRED[1][2]

    Standard City of San Diego permit application form for solar PV installation.

  • Electrical Permit ApplicationREQUIRED[3][4]

    Electrical permit application required for all solar PV system installations.

  • Solar PV ChecklistREQUIRED[5][6]

    DSD-specific checklist form for solar PV permit submissions.

Plans & Diagrams(5)

  • Site PlanREQUIRED[7][8]

    Scaled drawing showing property layout, building footprint, and proposed solar array placement.

  • Roof Layout / Module PlanREQUIRED[9][10]

    Detailed plan showing individual module placement, dimensions, and spacing on the roof surface.

  • Single-Line Electrical DiagramREQUIRED[11][12]

    Electrical diagram showing PV system components, conductors, disconnects, and utility interconnection.

  • Three-Line Electrical DiagramOPTIONAL[13][14]

    Detailed electrical diagram showing all conductors, grounding, and protection devices.

  • Structural Attachment DetailREQUIRED[15][16]

    Cross-section drawing showing how solar racking attaches to the roof structure.

Supporting Documents(5)

  • Module Specification SheetREQUIRED[17][18]

    Manufacturer specification sheet for the solar modules being installed.

  • Inverter Specification SheetREQUIRED[19][20]

    Manufacturer specification sheet for the inverter(s) being installed.

  • Racking Specification SheetREQUIRED[21][22]

    Manufacturer specification and engineering letter for the racking/mounting system.

  • Structural Engineering LetterOPTIONAL[23][24]

    Letter from a licensed structural engineer confirming the roof can support the proposed system.

  • Load Calculation WorksheetREQUIRED[25][26]

    Calculation showing existing electrical load and capacity for the solar system addition.

Photos & Labels(2)

  • NEC Labeling PlanREQUIRED[27][28]

    Plan showing locations and content of all required NEC warning labels and placards.

  • Existing Electrical Panel PhotoREQUIRED[29][30]

    Photograph of the existing main electrical panel showing available breaker spaces and labeling.

This checklist is for reference only. Requirements may change — always verify with San Diego before submission.

Ready to build your permit packet?

Answer a few quick questions and we'll generate your personalized checklist, templates, and submission plan for San Diego.

Start Permit Builder

No account required to get started

Also for San Diego Solar PV

Solar PV Permits in Nearby Cities

Chula VistasoonOceansidesoonEscondidosoon